Overview of work for the week completed as of 2/19/16

            The door frames have been installed and drywall is complete and textured in the new space. We have painted the ceiling in the new gym and have begun walls in the north class rooms.  IT room is ready for the switch over.  We have begun some of phase 1 demo by opening up the new doors and closing the existing doors.

 Two Week Looking Ahead

            We should be complete with the heavy masonry demo by the end of this coming week and ready for our phase 1 demo.  We will want to start construction on the cry room build-out next week and infill the current doors so that we can order glass for the room.  We will continue to paint and will start with our ACT install.